Prop 2 and the Five-Year Facilities Master Plan
What Prop 2 requires
Proposition 2 (November 2024) was implemented by AB 247, which added Education Code 17070.54.
A district participating in the School Facility Program must submit a five-year school facilities master plan approved by its governing board.
It is submitted to the Office of Public School Construction (OPSC) with Form SAB 50-MP.
A board approved plan supports applications for five years.
Master plan checklist
| Requirement | Reference | Status | Document |
|---|---|---|---|
| Board approval of the plan | 17070.54(a) | Document pending | Document pending |
| Eligibility for state bond funding | 17070.54(b) | Document pending | Document pending |
| Inventory of facilities For each instructional building, year built, square feet, year last modernized; number and age of portables; whether each school has a cafeteria or multipurpose room, library and gymnasium. | 17070.54(c)(1) and (d) | Document pending | Document pending |
| Existing classroom capacity | 17070.54(c)(2) | Document pending | Document pending |
| Projected enrollment for the next five years | 17070.54(c)(3) | Document pending | Document pending |
| Capital planning budget | 17070.54(c)(4) | Document pending | Document pending |
| Financing and funding sources Including lead testing and remediation. | 17070.54(c)(5) | Document pending | Document pending |
| Verification of current assessed value | 17070.54(c)(6) | Document pending | Document pending |
| Board certified deferred maintenance plan | 17070.54(c)(7) | Document pending | Document pending |
| Narrative on consistency with the LCAP State priority 1, facilities in good repair. | 17070.54(c)(8) | Document pending | Document pending |
| Form SAB 50-MP Five-Year Master Plan Checklist. | OPSC | Document pending | Document pending |
Prop 2 candidate projects
Showing 22 of 22 candidate projects.
| School | Project type | Square feet | Status |
|---|---|---|---|
| Alta Loma High School | Modernization | 213,000 | Candidate, eligibility to be confirmed |
| Alta Loma High School | New Construction | 15,000 | Candidate, eligibility to be confirmed |
| Chaffey High School | Modernization | 546,440 | Candidate, eligibility to be confirmed |
| Chaffey High School | New Construction | 38,500 | Candidate, eligibility to be confirmed |
| Colony High School | Modernization | 243,400 | Candidate, eligibility to be confirmed |
| Colony High School | New Construction | 38,000 | Candidate, eligibility to be confirmed |
| Etiwanda High School | Modernization | Pending verification | Candidate, eligibility to be confirmed |
| Etiwanda High School | New Construction | 18,500 | Candidate, eligibility to be confirmed |
| Los Osos High School | Modernization | 291,200 | Candidate, eligibility to be confirmed |
| Los Osos High School | New Construction | 16,000 | Candidate, eligibility to be confirmed |
| Montclair High School | Modernization | 228,000 | Candidate, eligibility to be confirmed |
| Montclair High School | New Construction | 38,500 | Candidate, eligibility to be confirmed |
| Ontario High School | Modernization | 221,700 | Candidate, eligibility to be confirmed |
| Ontario High School | New Construction | 7,285 | Candidate, eligibility to be confirmed |
| Rancho Cucamonga High School | Modernization | 40,292 | Candidate, eligibility to be confirmed |
| Rancho Cucamonga High School | New Construction | 14,000 | Candidate, eligibility to be confirmed |
| Valley View High School | Modernization | 26,000 | Candidate, eligibility to be confirmed |
| Chaffey Adult School | Modernization | 19,200 | Candidate, eligibility to be confirmed |
| Chaffey District Online High School and Alternative Education Center | Modernization | 19,680 | Candidate, eligibility to be confirmed |
| Chaffey District Online High School and Alternative Education Center | New Construction | 6,000 | Candidate, eligibility to be confirmed |
| Adult Education Center (7th Street) | Modernization | 19,680 | Candidate, eligibility to be confirmed |
| District Growth | New Construction | 220,000 | Candidate, eligibility to be confirmed |
No candidate projects match these filters.
Source: 2026 Facilities Master Plan Update draft. Projects are listed for planning purposes. State eligibility is determined through OPSC.
Document library
Reference documents
- Education Code 17070.54 (opens in a new tab)
- OPSC Five-Year School Facilities Master Plan Guidelines (Rev. January 2026) (opens in a new tab)
- OPSC School Facility Master Plans resources (opens in a new tab)
- OPSC Proposition 2 and AB 247 (opens in a new tab)
- 2012 Facility Master Plan (PDF) (opens in a new tab)
- CBOC Financial and Recently Completed Projects Report, October 22, 2026 (opens in a new tab)
- Measure P Bond Audit Report 2025 (fiscal year ended June 30, 2025) (opens in a new tab)
District documents
- Board resolution approving the plan To be posted
- Form SAB 50-01 Enrollment Certification/Projection To be posted
- Form SAB 50-02 Existing School Building Capacity To be posted
- Form SAB 50-03 Eligibility Determination To be posted
- County gross assessed value verification To be posted
- Board certified deferred maintenance plan To be posted
- LCAP To be posted
- Demographic study To be posted
- Form SAB 50-MP To be posted