South Hall Modernization
- Scope as described in source
- Complete interior modernization of a 1937 three story classroom building with voluntary seismic upgrades (new footings, shotcrete shear walls), electrical, windows, ceilings, restrooms, fire alarm, LED lighting, AV and ADA work.
- Architect
- PJHM Architects
- Status as stated in source
- Completed December 2022 (per program manager).
- Key date
- December 2022
- Source
- Tilden Coil; Measure P project page
View source (opens in a new tab)